Factory Acceptance Test (FAT) document
460 530 625
As the system is ready to be handed over, a FAT meeting with the orderer is summoned. Include me in the invitation for the test even though I usually won't attend the test itself but only check the minutes of the test. Proposals for testing arrangements and record of the tests are attached with the summons for approval.
During the test, the orderer's representative writes down any anomalities or discrepancies to Comments column and signs each step of the FAT procedure with his/hers initials and date as the test proceeds. Even if the discrepancy is reasoned and the function of the system is relevant and correct in functional sense, it is commented to the record. With his/her signed comment the discrepancy (or change) is either accepted or rejected. All the rejected items must be checked and rectified immediately after the FAT and tested again. If the discrepancies call for major changes in the application a new FAT is summoned later.
As the FAT has been run succesfully the FAT records are scanned and saved to Moodle in PDF format.
Initial conditions | Tested function | Actions | Results | Comments |
---|---|---|---|---|
The sootblower is at rest at the IN LIMIT (= GS-01 is activated), the STEAM VALVE V-02 is closed, STAEM SENSOR FS-03 is deactivated | Automatic soot blowing | Soot Blowing is started by pushing START BUTTON XS-04 momentarily. | STEAM VALVE V-02 control output is activated. MOTOR M-05 sontrol OUT is activated, OUT lamp GI-06 starts to blink at 1 Hz. | |
Steam flow | Steam flow is simulated by closing STEAM SENSOR FS-03 | STEAM lamp FI-07 is lit. | ||
Soot blower reaches OUT LIMIT | OUT LIMIT GS-08 is activated | MOTOR M-05 control OUT is deactivated, OUT lamp GI06 is constantly lit. After 5 seconds the soot blower MOTOR M-05 control IN is activated, IN lamp GI-09 starts to blink at 1 Hz. | ||